Incheon New Port

The Best Port Infrastructure and Service Incheon New Port, the greatest project of Incheon Port

Since 2009, the project has developed the ocean side of Songdo International City (IFEZ) to construct exclusive docks for large containers as container ships are getting bigger. This will enable Incheon Port to emerge as the key port of the Pan-Yellow Sea area
Incheon New Port
Development plan
Incheon New Port
Incheon New Port(Stage1) Development plan
  • Budget : $2.25 billion
  • Project period : 2007 ~ 2020
  • Cargo-handling capacity (containers): 2.1 million TEU/year
  • Project details : Six berths(3,000 TEU x 2, 2,000 TEU x 4)
    • Up to 12,000 TEU-class, seaway depth : 16 meters
  • Project details

    Government : Shore protection : 15.9km / managed wharf : 410m / entry ramp : 6.8km / background lot : 530,000㎡, etc

    - IPA: Container wharf : 1,600 meters (six berths), background lot : 1.59 million ㎡

  • Inquiries

    Port Development Team, Incheon Port Authority ☎ 032-890-8155

    Infrastructure Service Industry Division, IFEZ Authority ☎ 032-453-7323

Status of Stage 1-1
Status of Stage 1-1 : Classification, HJIT, SNCT
Classification HJIT SNCT
Operating companies Hanjin Incheon Container Terminal Co., Ltd Sunkwang Newport Container Terminal Co., Ltd.
Details : Quay 800 meters, CY construction: 480,000 ㎡ 3,000 TEU×1, 2,000 TEU×2 800 meters, CY construction: 480,000 ㎡ 3,000 TEU×1, 2,000 TEU×2
Operation period 30-year lease after opening (2015)
Plans for developing New Port
Plans for developing New Port
New Port Stage Ⅰ-2 After 2020 Container Four berths of 2,000 TEU class,
Two berths of 4,000 TEU class
New Port Stage Ⅱ After 2030 Container Two berths of 2,000 TEU class,
11 berths of 4,000 TEU class
Accessories Three berths of 20,000-ton class,
one berth of 50,000-ton class
Plans for developing New Port’s background lot
Plans for developing New Port’s background lot
StageⅠ 2020 2,144,000㎡
StageⅠ-2, Ⅱ, Ⅲ Future 4,047,000㎡