본문 바로가기

Knowledge Information Industry Park
The organic linkage between knowledge-based manufacturing, services, and R&D leads to creation of the industrial complex and economic benefits
Business Outline
  • LocationSongdo District Zone 4
  • Size2,401,744.7㎡
  • Project Period2003 - 2020
  • Project detailsEstablishment of industrial parks to secure knowledge-based manufacturing and R&D linkage
  • Total project cost555.5 billion won
  • Implemented byIncheon Metropolitan City
1. Songdo Techno Park Termination

Located in the International Business Complex, Northeast Asia Trade Tower is a landmark in Songdo with 71 floors and both business facilities and a hotel.

  • Size453,523㎡
  • Project detailsVenture building (tidal tower), pilot production plant, university research center, corporate research institute, etc. Venture start-up, auto parts industry cluster support, etc.
  • Implemented bySongdo Techno Park
  • Project Period2001 - 2005
Current Status of Major Foreign Investment Companies
2-1. Gudel Linear Tec Inc.Termination
  • Project nameConstruction of an industrial robot production facility
  • Location7-15, Incheon tower-daero 25beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size11,279㎡(Total floor area: 4,856㎡)
  • Project detailsIndustrial Precision Machinery Manufacturing
  • Project cost3 billion won (Foreign invested amount: US$0.25 million)
  • Investor100% backed by Gudel Group AG of Switzerland
  • Project Period2005. 06 - 2007. 12
2-2. CelesticaTermination
  • Project nameManufacturing and research of equipment for LCD and Solar Cell production
  • Location105, Venture-ro, Yeonsu-gu, Incheon, Republic of Korea
  • Size16,008㎡(Total floor area : 9,991㎡)
  • Project detailsSemiconductor production machinery manufacturing
  • Project cost20 billion won (coat amount: US$30 million)
  • Investor100% backed by coat company A-1 Machine (USA)
  • Project Period2007. 09 - 2008. 10
2-3. Cotech Inc.Termination
  • Project name Industrial Display Monitor Manufacturing and Research
  • Location26, Venture-ro 24beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size19,249㎡(Total floor area : 19,459㎡)
  • Project detailsProduction of LCD, PDP, gaming/medical device monitors
  • Project cost23 billion won (coat amount: US$10 million)
  • InvestorHong Kong, Hsin Chong Construction Group Ltd.
  • Project Period2007. 07 - 2009. 02
2-4. Huneed TechnologiesTermination
  • Project nameAerospace & Ubiquitous & Tactical Communications & NCO Equipment Manufacturing & Research
  • Location87, Venture-ro, Yeonsu-gu, Incheon, Republic of Korea
  • Size25,946㎡(Total floor area : 27,388㎡)
  • Project detailsManufacturing and research of communications/information electronic devices related to the defense industry
  • Project cost33.7 billion won (coat amount: USD 20 million)
  • InvestorUnited States of America, The Boeing Company
2-5. Kyobo Data CenterTermination
  • Project nameKyobo-IBM Data Center
  • Location14, Venture-ro, Yeonsu-gu, Incheon, Republic of Korea
  • Size8,343㎡(Total floor area : 10,866㎡)
  • Project detailsIDC Center, Computer Data Processing, Server Hosting Service
  • Project cost28.5 billion won (coat amount: USD 10 million)
  • InvestorUnited States of America, Pine Tree Equity
  • Project Period2008. 03 - 2009. 09
2-6. Mandohellla ElectronicsTermination
  • Project nameAdvanced auto parts production facilities and research
  • Location224, Harmony-ro, Yeonsu-gu, Incheon, Republic of Korea
  • Size26,526.9㎡(Total floor area : 15,338㎡)
  • Project detailsECU(Electronic Control Unit), DAS(Driver Assistance System) etc.
  • Project cost220 billion won (coat amount: USD 250 million)
  • InvestorGermany, Hella Electronics
  • Project Period2008. 03 - 2009. 09
2-7. FiboxTermination
  • Project nameDigital Contents (Animation) Industrial Accumulation Facility Construction and Development
  • Location17, Harmony-ro 177beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size5,108㎡ (Total floor area 26,797㎡)
  • Project detailsDigital content (animation) creation, planning, production and distribution
  • Project cost31.7 billion won
  • InvestorHong Kong JUNA International Ltd.
  • Project Period2008. 08 - 2013. 04
2-8. Songdo Ani Park Termination
  • Project nameDigital Contents (Animation) Industrial Accumulation Facility Construction and Development
  • Location17, Harmony-ro 177beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size5,108㎡ (Total floor area 26,797㎡)
  • Project detailsDigital content (animation) creation, planning, production and distribution
  • Project cost31.7 billion won
  • InvestorHong Kong JUNA International Ltd.
  • Project Period2008. 08 - 2013. 04
2-9. KyungshinTermination
  • Project nameResearch and manufacture of next-generation automotive electronic components
  • Location105, Venture-ro, Yeonsu-gu, Incheon, Republic of Korea
  • Size16,008㎡
  • Project detailsProduction and research of core parts for eco-friendly armature automobiles
  • Project cost103.8 billion
  • InvestorJapan Sumitomo
  • Project Period2010.10 - 2012. 01
2-10. Sanil TechTermination
  • Location43-10, Incheon tower-daero 25beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size7,793.5㎡
  • Project detailsLED Parts Production
  • Project cost11 billion won
  • InvestorJapan IQ Corporation
  • Project Period2005. 03 - 2007. 08
2-11. RittalTermination
  • Location11-20, Songdo-dong, Yeonsu-gu, Incheon, Republic of Korea
  • Size8,700.1㎡
  • Project detailsIndustrial enclosure manufacturing and development
  • Project cost22 billion won
  • InvestorGermany Rittal
  • Project Period2010. 03 - 2014. 10
2-12. PiolaxTermination
  • Location47, Harmony-ro 187beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size5,413.3㎡
  • Project detailsAutomobile parts manufacturing and R&D
  • Project cost15.6 billion won
  • InvestorJapan Piolax
  • Project Period2013. 01 - 2014. 10
2-13. ellermannTytonTermination
  • Location28, Venture-ro 12beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Size4,160㎡
  • Project detailsAutomobile parts manufacturing and research
  • Project cost14.4 billion won
  • InvestorUnited Kingdom HellermannTyton
3. Songdo Shinsegae Mall
  • Location10-1~6, 10-11~14 Songdo-dong
  • Size59,730㎡
  • Total project costabout 500 billion won
  • Implemented byIncheon Shinsegae Co., Ltd
  • Project Period2016 - 2021
  • Project detailsUrban lifestyle shopping complex