On Wednesday, October 14, 2020, IFEZ held a roundtable on the construction of Cheongna Haneul Bridge (Third Link Bridge) with representatives from 15 local construction companies in Incheon. IFEZ explained the project background, the original design plan, the technical proposal bidding method for detailed design, and the future schedule, while requesting participation by local companies in consortium formation. Cheongna Haneul Bridge (Third Link Bridge) was scheduled to begin construction at the end of 2020 and be completed in 2025, and it was planned as a bridge with a total length of 4.67 kilometers, a width of 29 meters, six lanes, sidewalks, and bicycle paths.