Bio-complex
We concentrate on medical tourism, medical devices, biopharmaceutical production, and R&D, with an emphasis on personalized medicine and regenerative medicine on an international level
Business Outline
  • LocationSongdo District Zone 4
  • Size1,316,962.3㎡
  • Project Period2003 - 2023
  • Project detailsEstablishment of a high-tech Bio-Complex
  • Total project cost16.8 billion won
  • Implemented byIncheon Metropolitan City
1. Celltrion Termination
  • Project nameEstablishment of bio-pharmaceutical manufacturing and research facilities
  • Location201-2 Songdo-dong, Yeonsu-gu, Incheon, etc.
  • Area190,706㎡
  • Project costabout 2.1 trillion won
  • InvestorSingapore Temasek
  • Project Period2002 - 2011
2. Janssen Termination
  • Project nameEstablishment of a pediatric vaccine manufacturing and research facility
  • Location23, Harmony-ro 303beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Area33,575㎡
  • Project costabout 95 billion won
  • InvestorUnited States of America Johnson&Johnson
  • Project Period2008 - 2011
3. iSens Termination
  • Project nameManufacturing of blood glucose equipment and the establishment of a research facility
  • Location12, Harmony-ro 275beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Area6,560㎡
  • Project costabout 25.4 billion won
  • InvestorJapan Arkray
  • Project Period2007 - 2011
4. KD Corporation Termination
  • Project nameEstablishment of a pharmaceutical separation device manufacturing facility
  • Location34, Harmony-ro 275beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Area9,139㎡
  • Project costabout 23 billion won
  • InvestorUnited States of America RE SPINE
  • Project Period2008 - 2010
5. EONE Life Science Research Institute Termination
  • Project nameEstablishment of a Laboratory Diagnostic Techniques Research Institute
  • Location291, Harmony-ro, Yeonsu-gu, Incheon, Republic of Korea
  • Area5,032㎡
  • Project costabout 8.7 billion won
  • Project Period2010 - 2012
6. Daifuku Korea Termination
  • Project nameEstablishment of Daifuku's Logistics Automation System R&D Center
  • Location8, Harmony-ro 275beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Area5,032㎡
  • Project costabout 12 billion won
  • Project Period2010 - 2013
7. Enviro Technology Termination
  • Project nameVeolia Water Asia Pacific Water Treatment Professional Education and Training Center
  • Location6, Songdogukje-daero 372beon-gil, Yeonsu-gu, Incheon, Republic of Korea
  • Area3,300㎡
  • Project costabout 7 billion
  • Project Period2011 - 2013