What is Songdo International City Waterfront Project?
  • Making citizens healthy!
    (through water quality improvement)
    • Seawater exchange system
    • Improvement of reservoir water quality
  • Keeping citizens safe!
    (having a disaster prevention facility)
    • Installation of flood gates and water reservoir-related facilities
    • Ensuring rainwater storage capacity by dredging runoff water
  • For enriching lives of citizens
    (Enjoyable water facilities)
    • Utilization of the waterside area at the reservoir
    • Positioning to become marine tourism city
Business Outline
  • Waterfront Construction Project
    • Size : Waterway extension 21.17 km, waterway width 40-500m (water area 4.66㎢)
    • Major facilities : Bridges, sluice gates, connecting waterways, waterside decks, lock gates, marina facilities, site construction, etc.
    • Project cost : KRW 621.5 billion
    • Business period : 2012 - 2027
  • Phase 1
    • Size : Waterway extension 10.46 km, waterway width 40-500m (water area 2.81㎢)
    • Main facilities : Bridges, sluice gates, connecting waterways, artificial beach, water deck, etc.
    • Business period : 2019- 2025
  • Phase 2
    • Size : Waterway extension 5.73 km, waterway width 300m (water area 1.85 ㎢)
    • Main facilities : Sluice gates, lock gates, marina facilities, site construction, etc.
    • Business period : 2025- 2027
  • District 11 (Separate project)
    • Size : Waterway extension 4.98 km, waterway width 40-60m (water area 0.4㎢)
    • Main facilities : Bridges, sluices, connecting waterways, waterside decks, etc.
    • Business period : 2018- 2027