Major Projects
-
홈
-
-
-
Business Outline
- LocationSouth side of Cheongna International City
- Size1,170,000㎡
- Total project cost391 billion won
- Implemented byKorea Land & Housing Corporation (LH)
- Project Period2006 - 2021
- Project detailsAttracting local and foreign investment with an emphasis on R&D related to automotive high-tech parts and materials
- Progress Status
- 2014.02 : Start of Zone 1 Infrastructure construction
- 2015.12 : Start of Zone 2 Infrastructure construction
- 2016.12 : Zone 1 Land Supply
- 2020.06 : Zone 1 Infrastructure work completed
- 2021.06 : Approval of changes to development plans and implementation plans
- 2022.03 : Zone 2 Infrastructure construction completed
- 2022.04 : IHP Urban Industrial Park Management Master Plan Change Notice
- Department in chargeYeongjong Cheongna Planning Division Cheongna Planning Team (032-453-7613)