Cheongna Lake Park
Business Outline
  • LocationCheongna International City
  • Size693,000㎡
  • Total project cost78.5 billion won
  • Implemented byKorea Land & Housing Corporation
  • Project Period2012 - 2015
  • Project detailsCircular trail, large musical fountain underwater plaza, floor fountain, music facilities
  • Progress Status
    • 2012.06 : Start of construction
    • 2014.09 : Temporary opening of landscaping facilities
    • 2015.12 : Construction completed
  • Department in chargeCheongna Management Division Park Development Team(032-453-7682)