Business Outline
  • LocationB4, B5, A5, 25, Cheongna International City
  • Size159,000㎡ (48,000 pyeong)
  • Total project cost1.1996 trillion won
  • Implemented byCheongna Int'l Financial Complex
  • Project Period2015.06 - 2025.08
  • Project detailsBusiness (finance), apartment housing, officetels, hotels, cultural facilities, shopping mall, etc.
  • Progress Status
    • 2015.08 : Signed a business agreement (LH↔Hanyang Consortium)
    • 2016.01 : Signed a land sale contract (LH↔Hanyang Consortium)
    • 2016.08 : Commencement of apartment housing construction
    • 2019.03 : Apartment housing completed
    • 2019.10 : Business Facility (Building A) Building Permit obtained
    • 2019.11 : Commencement of construction of Business facility (Building A)
    • 2021.08 : Commencement of construction of Business facility (Building B)
    • 2021.11 : Officetel sale and construction